top of page
Collaborating.png

Pumping Plants & Laterals

Preliminary designs from the East Columbia Basin Irrigation District (ECBID) identified an initial 9 pumping plants and laterals at an estimated cost of up to $400 million. 

​

Construction of each lateral goes through several phases: planning, design, engineering, and construction. Landowners can be involved in the planning and design phase in order to ensure that they will be able to hook up to the new irrigation system. We know from experience that organizing or working with a group of neighbors in the early stages of planning and design is critical if you want your specific needs factored into the design. 

 

For most of the laterals, nothing is set in stone. If you have an alternative that is technically and operationally feasible, it would be in your best interest to form a working group among neighbors with similar needs and be part of the process.  

​

​

​

23-08-22 OGWR.png

Status of Each Pumping Plant & Lateral

Updated September 20, 2023 by Jennifer Hickenbottom, Bureau of Reclamation

2-WSDA-Derek Sandison, Madi Moore at LC2 8-3-2020.JPG

Lateral 11.8

Current Status:
30% Designs accepted by Reclamation, ECBID, and Ecology - April 14, 2022. System now moving towards 60% Designs.

​

Engineering Sketch

Lateral 22.1

Current Status:
60% Designs accepted by Reclamation, ECBID, and Ecology - April 19, 2023. System now moving towards 90% Designs. Final cultural report received from IRZ; Cultural consultation processes has begun. Environmental compliance documentation drafted and easement acquisition process progressing.

2-WSDA-Derek Sandison, Madi Moore at LC2 8-3-2020.JPG

Lateral 40.2

Current Status:
Engineering phase has not begun.

​

26-EL47.5 Pumps 9-21-2020.JPG

Lateral 47.5

Current Status:
Completed; irrigation on the ground and still adding acres.  Contact ECBID for more information.

2-WSDA-Derek Sandison, Madi Moore at LC2 8-3-2020.JPG

Lateral 54

Current Status:
Engineering phase has not begun.

​

​

2-WSDA-Derek Sandison, Madi Moore at LC2 8-3-2020.JPG

Lateral 73.3

Current Status:
Engineering phase has not begun.

​

Engineering Sketch

Lateral 80.6

Current Status:

30% Designs accepted by Reclamation, ECBID, and Ecology - December 20, 2022. System now moving towards 60% Designs. Anticipate physical model to be completed in September 2023. Easement acquisition process started. 

Engineering Sketch

Lateral 84.7

Current Status:

30% Designs accepted by Reclamation, ECBID, and Ecology - January 10, 2023. System now moving towards 60% Designs. Physical model completed in June 2023. Easement acquisition process started.

Engineering Sketch

Lateral 86.4

Current Status:

30% Designs accepted by Reclamation, ECBID, and Ecology - June 29, 2023. 60% Designs received on September 1, 2023. 60% designs currently in design review stage. Easement acquisition process well underway. Cultural and environmental compliance processes started.

​

bottom of page